Less
holiday travel expected
by
Despite troublesome flooding in the Beloit,
most of the summer construction projects have
been able to carry on without interruption.
“All of our construction projects have
not been right up against the river,”
said City Engineer Mike Flesch. “They've
been progressing as scheduled.”
The construction on West Hart Road is completed
and is open to the public, Flesch said. West
Hart Road was completely reconstructed with
a new water main, sanitary and storm sewer,
curb and gutter, sidewalks, concrete pavement,
and decorative lights.
Though gravel placement on St. Lawrence Avenue
was delayed because of weather, it has been
placed and construction throughout the streets
of West Side Initiative is moving along.
“The weather has not been a real significant
hindrance,” Flesch said. “We may
have lost one day.”
The West Side Initiative includes St. Lawrence
Avenue from Fourth Street to Vine Street and
Vine from St. Lawrence to Roosevelt Avenue.
Crews placed electrical lighting and conducted
final cleanup and are now working on the placing
curb and gutter.
On the East Side Initiative, which includes
Bushnell Street to Park Avenue to Central Avenue
and Harrison Avenue from Grand Avenue to Emerson
Street, the underground work is currently being
completed and all pavement, curbs and gutters
have been removed. The construction is expected
to be complete by mid-August.
The area of Burton Street from McKinley Avenue
to Sixth Street will be completely constructed
starting mid-July, Flesch said. The construction
will include a new curb and gutter, water main
extension, asphalt pavement, decorative street
lights, and sidewalks. An off-street bike and
pedestrian path that connects the riverfront
with the Boys and Girls Club and Krueger Park
will also be constructed. The area of Burton
Street from Madison Road to McKinley Avenue
is still closed to through traffic. Flesch said
the new water main is well underway, and replacement
of curb and gutter and new asphalt pavement
will also be completed soon.
On Public Avenue, three colors were selected
for the ribbons of color concrete that will
be placed on the sidewalk area in front of the
Beloit Vision Center. The three colors are straw,
onyx, and an apple red. Crews are working to
pour the concrete and finish up road repairs,
which were completed recently, Flesch said.
Tree removal is currently under way on Eclipse
Boulevard, and crews are working on the interior
demolition of the new Beloit Public Library.
While most of the construction has been able
to go on as scheduled, flooding has set back
a couple of projects, Flesch said. The Riverside
Shoreline Stabilization, which was supposed
to start earlier this summer, has been delayed
due to high water levels. The stabilization
is set to begin in September barring any more
flooding issues, Flesch said. The project includes
repairing of the erosion near mid-lawn shelters,
planting native species shoreline plants and
flowers, cleaning debris from the river bank,
and installing informational and educational
signs.
The construction of a canoe and kayak launch
in the Chester Square parking lot has also been
delayed until the river recedes. Once completed,
the launch will be open to all residents, but
the city will not provide canoes or kayaks.
Flesch is hoping the launch will be constructed
by the fall.
Construction updates are posted weekly on the
city's Web site.
|
|